Isolate, prove dead, lock off. Do it before every electrical test on a boiler, from a thermistor to a pump winding.

Before you start

Safe isolation, proving dead and locking off. Do it before every test in this guide.

Why it comes first

Every dead test in this guide, from a thermistor to a pump winding, assumes the boiler has been isolated and proved dead. A reading taken on a live circuit means nothing, and it can kill the meter or you.

The dead test proves one thing: the circuit you tested, at the moment you tested it, is dead. Lock it off so it stays that way.

The kit

Not for proving dead

Stop.

A multimeter. On the wrong setting, or with its fuse gone, it shows 0 V on a live circuit. Some older boiler manuals still say to prove dead with a meter on AC volts. Gas Safe TB 118A says use a two-pole indicator and a proving unit, for exactly that reason. Follow the bulletin.

A socket tester or a non-contact detector on its own. A non-contact detector finds a live case. It can't prove a circuit dead.

What to isolate

The boiler should be on a double-pole fused spur with a 3 A fuse. Some manufacturers ask for a contact gap of at least 3 mm on both poles. The other accepted way is a plug with a 3 A fuse in an unswitched socket: pull it and take its fuse with you.

Controls are not always on the same supply. A wiring centre, a pump or a programmer can be fed from a different spur. Find every feed before you open the wiring centre. Where there’s more than one isolator, each should have a label saying where the others are.

Before you take off any gas part, turn off the gas at the appliance isolation valve as well.

Locked off at the fused spur. Switch off, fuse carrier out, lock-off and padlock on, tag on the padlock.

Illustration. Locked off at the fused spur. Switch off, fuse carrier out, lock-off and padlock on, tag on the padlock.

Two-pole indicator on its proving unit, every light on. Prove it before and after the dead test.

Illustration. Two-pole indicator on its proving unit, every light on. Prove it before and after the dead test.

If you find a fault

A case or pipe that shows live: don't touch it, and warn everyone in the house. Switch off that circuit and check again. Still live, or you can't find the circuit? With the customer's say-so, switch off at the main switch and leave a written notice that it stays off until an electrician has tested it. Don't fault find on top of it.

Safe isolation, step by step

Test, prove, test. One: prove the two-pole tester on the proving unit, both probe tips on its contacts, the lights show. Two: test the boiler terminal strip L to N, L to E and N to E, no lights. Three: prove the tester on the proving unit again.

Test, prove, test. Prove the indicator on the proving unit, test all three pairs at the boiler, then prove the indicator again. If it fails the second proving, the dead test means nothing: start again with a working tester.

Isolate and prove dead

  1. Tell the customer. Say what you're switching off and for how long. Fridges and alarms can share a circuit.
  2. Live Safe to touch. Check the detector on a known live source. Run it over the case, pipes and controls, then check it on the live source again before you touch anything. Never a neon screwdriver.
  3. Find the isolation point. Spur, plug or MCB. Check it feeds the boiler, then look for other feeds to the controls.
  4. Check the tester. Leads and probes to GS38, undamaged, finger guards on. Prove it on the proving unit.
  5. Isolate. Switch off and take the fuse out. Keep the fuse in your pocket.
  6. Lock off and label. Lock on the spur or MCB, padlock on, label on.
  1. Test at the boiler. At the terminal strip: L to N, L to E, N to E, probe on earth first for the earth pairs. No lights on any pair.
  2. Prove the tester again. Same tester, same proving unit. All lights show.
  3. Start work. The lock stays on until you're ready to power up, even if you go to the van.

Stop.

Lights on any pair at step 7? Something is still feeding the boiler. Find it before you go on.

Putting the power back

  1. Dead checks first. Earth continuity, short circuit and resistance to earth, all with the fuse still out. Chapter 2 has the settings.
  2. Fuse in. Refit a 3 A fuse, never the 13 A one you sometimes find there.
  3. Live Polarity. L to N, L to E, N to E at the terminal strip with no demand. Chapter 2 shows what the readings mean.
  4. Run it. Run the boiler on heating and hot water and check it does what the customer asked for.

Gas parts

Isolate the electrics and the gas before you change any part, and recommission the boiler afterwards. After any work on the gas side, tightness test and check the combustion before you leave it. Chapter 8 has the checklist.

Bridging a safety device to get a boiler running, even for a minute to prove a point, leaves it unsafe. Test the device instead.

Free guide

Get Fault Finding Basics as a PDF

This lesson is part of Fault Finding Basics, our free 26-page guide: safe isolation, your meter, how a combi works and the five tests that find most faults. Add your email and it comes straight over.

Send me the guide

Want every test? The Flint Field Guide has all 56 chapters with a video for every test. £97 once, updates included.

All fault finding lessons

For competent, Gas Safe registered engineers. Isolate and prove dead before any electrical test. Always work to the manufacturer's instructions and the current standards, and check every figure against the appliance data badge and manual.